Waingapu shrimp farm nearly 20% built, aims to open in 2028

The Rp7.2 trillion project in East Sumba is due at 50% in December. The ministry expects construction to end in late 2027 and operations in early 2028.

By The Sumba Times deskPublished 3 min read
A boat on the shore at Padadita, Waingapu. File photo.
A boat on the shore at Padadita, Waingapu. File photo. Photo: 06Ivonne (CC BY-SA 4.0)
Quick answer

The integrated shrimp farm that Indonesia's Ministry of Marine Affairs and Fisheries (KKP) is building at Waingapu, East Sumba, was close to 20% complete in early November 2026, CNBC Indonesia reported on 8 November. The ministry wants 50% by December 2026, construction finished by the end of 2027 and operations from early 2028, at a planned 52,800 tonnes of shrimp a year.

Key points
  • CNBC Indonesia reported on 8 November 2026 that construction was close to 20% complete; the target for December 2026 is 50%.
  • The contract was shortened from three years to two at the request of President Prabowo Subianto, so building must finish by the end of 2027 and operations start in early 2028.
  • The site covers about 2,150 hectares in Pandawai district: 12 clusters, 1,536 culture ponds, 192 reservoir ponds and 48 wastewater treatment units.
  • Investment is US$500 million (about Rp7.2 trillion); target output is 52,800 tonnes of shrimp a year at full operation.
  • Earlier reports cite about 3,000 local workers to be trained and around 7,000 jobs across the supply chain; none of the new reports covers environmental impact.

WAINGAPU. The integrated shrimp farm under construction at Waingapu, East Sumba, is close to 20% complete, according to CNBC Indonesia, which reported on Sunday 8 November 2026 that the Ministry of Marine Affairs and Fisheries (KKP) wants it at 50% by December. The ministry expects construction to finish at the end of 2027 and the farm to start operating in early 2028. Times are WITA (UTC+8).

How far along is the Waingapu shrimp farm?

Tb Haeru Rahayu, KKP's Director General of Aquaculture, said progress was close to 20% in early November. The 50% target for December is measured by "material on site", meaning materials already delivered, and every part of the project is being built at once rather than one cluster after another. "We build it all at once, so progress is calculated overall," he said, in CNBC's translation of his remarks. InvestorTrust had reported 10% physical progress as of 29 July 2026, with more than 300 heavy equipment units on site. The reports do not say whether the two percentages use the same method.

The original contract ran for three years. CNBC reports that President Prabowo Subianto asked Minister Sakti Wahyu Trenggono to shorten it to two. Haeru said that in that case all construction must be finished by the end of 2027. A shrimp cycle takes about four months from stocking to harvest, so CNBC says the first harvest could come around mid-2028.

Sumba business and projects, weekly

Land, tourism figures, flights and new projects: what matters if you invest or work in Sumba. Neutral and sourced.

One email a week. No spam. Unsubscribe in one click. Sumba this week

What is being built in Pandawai district

The site covers about 2,150 hectares in Palakahembi village and Watumbaka urban village, in Pandawai district, according to KKP. CNBC lists 12 clusters, 1,536 culture ponds, 192 reservoir ponds and 48 cluster wastewater treatment units, plus a seawater intake, a quarantine area, production roads and processing facilities. KKP calls it roughly 20 times larger than its Kebumen farm in Central Java. Antara reported in April that the land was previously savanna.

The investment is US$500 million, about Rp7.2 trillion, financed through foreign private credit. Antara breaks it down as Rp6.1 trillion in foreign loans and Rp1.1 trillion in counterpart rupiah funds. At full operation the farm is meant to produce about 52,800 tonnes of shrimp a year, from two to 2.5 cycles annually.

Jobs and local hiring

KKP opened online recruitment for 3,000 local workers on 10 February 2026, with free training. In April, Nyoman Radiarta, who heads KKP's human resources agency, said the classes would last 12 to 16 months. On 2 September, Muhammad Qodari, head of the Government Communication Agency, said the project is projected to absorb about 7,000 workers across its industrial chain, which InvestorTrust says includes hatcheries, feed mills, cold storage and ice factories. Arif Maramba, head of Palakahembi village, called the project a "new economic engine" in KKP's press release.

What it means

The farm is an industrial project, not a tourism one, but it will shape the East Sumba economy, labour market and coastline around Waingapu for years. If it works as planned, it could increase demand for housing, transport and services; that is our reading, not a claim in the reports. The CNBC report does not address environmental impact or effects on neighbouring communities, and KKP's press release mentions only a wastewater treatment plant, greening and good aquaculture practices. We will report on those points when they are published. For other large works on the island, see what is being built in Sumba.

If you are travelling to Sumba

This is an industrial construction site, not a visitor attraction, and none of the reports mentions public access or tours. If you plan to invest, work or stay long term around Waingapu, the project is worth following: it will shape local jobs, transport and the coastline. For sightseeing, nothing changes for now.

Topics: Land and investment Waingapu and East Sumba

Planning a trip to Sumba? Our free guides cover when to go, how to get around, costs, safety and culture. Plan your trip →

Sumba business and projects, weekly

Land, tourism figures, flights and new projects: what matters if you invest or work in Sumba. Neutral and sourced.

One email a week. No spam. Unsubscribe in one click. Sumba this week

Related stories

File photo: a boat on the sand at low tide, Walakeri Beach, East Sumba, 2018. It does not show Salura or its port.

Business & investment

East Sumba opens small-vessel permit counter on Salura island

The Waingapu harbour master now measures boats and issues Pas Kecil permits in Salura port, but no fees or requirements are published.

· 2 min read
AI-generated illustration of a sugarcane field and a sugar mill on an island savanna; not a photo of PT MSM, of Umalulu or of the fire.

Business & investment

Police: cane waste self-ignited in fire at East Sumba sugar mill

Police say fermenting cane waste caught fire at 44°C at PT MSM in Umalulu and hit a conveyor building; damage, date and mill status are not reported.

· 2 min read
File photo: a blue fishing boat on the sand at Walakeri Beach, East Sumba, 2018. It does not show Salura or its jetty.

Business & investment

East Sumba regent heads to Salura island over Rp50 billion jetty repair

The Transport Ministry has approved Rp50 billion for the jetty damaged by Cyclone Seroja, but no start date has been announced.

· 2 min read
File photo of Waingapu port: a white tower on the shore and shipping containers at right. It does not show the governor's visit.

Business & investment

Governor inspects Waingapu port for direct shrimp and sugar exports

Governor Melki Laka Lena toured the port on 13 November, but no export dates, volumes, buyers or investments have been announced.

· 2 min read
File photo: a river near the Kambaniru Dam, Waingapu, East Sumba. It does not show Melolo, Lewa or the meeting described.

Business & investment

East Sumba asks for 2027 funds for Melolo and Lewa farm areas

The regent met the transmigration minister on 10 November and pitched sugar cane, cashew, seaweed and cattle, but no amounts have been announced.

· 2 min read
Savanna meets the sea near Waingapu, East Sumba.

Business & investment

East Sumba could issue NTT's first customary land certificate

Three customary communities have applied for communal land titles at the East Sumba land office. One file is nearly finished.

· 1 min read