# Waingapu shrimp farm nearly 20% built, aims to open in 2028

The Rp7.2 trillion project in East Sumba is due at 50% in December. The ministry expects construction to end in late 2027 and operations in early 2028.

- Source: The Sumba Times, https://thesumbatimes.com/en/projects/waingapu-shrimp-farm-nearly-20-percent-built-2028/
- Published: 2026-11-11
- Language: en

**Quick answer:** The integrated shrimp farm that Indonesia's Ministry of Marine Affairs and Fisheries (KKP) is building at Waingapu, East Sumba, was close to 20% complete in early November 2026, CNBC Indonesia reported on 8 November. The ministry wants 50% by December 2026, construction finished by the end of 2027 and operations from early 2028, at a planned 52,800 tonnes of shrimp a year.

The integrated shrimp farm under construction at Waingapu, East Sumba, is close to 20% complete, according to CNBC Indonesia, which reported on Sunday 8 November 2026 that the Ministry of Marine Affairs and Fisheries (KKP) wants it at 50% by December. The ministry expects construction to finish at the end of 2027 and the farm to start operating in early 2028. Times are WITA (UTC+8).

## How far along is the Waingapu shrimp farm?

Tb Haeru Rahayu, KKP's Director General of Aquaculture, said progress was close to 20% in early November. The 50% target for December is measured by "material on site", meaning materials already delivered, and every part of the project is being built at once rather than one cluster after another. "We build it all at once, so progress is calculated overall," he said, in CNBC's translation of his remarks. InvestorTrust had reported 10% physical progress as of 29 July 2026, with more than 300 heavy equipment units on site. The reports do not say whether the two percentages use the same method.

The original contract ran for three years. CNBC reports that President Prabowo Subianto asked Minister Sakti Wahyu Trenggono to shorten it to two. Haeru said that in that case all construction must be finished by the end of 2027. A shrimp cycle takes about four months from stocking to harvest, so CNBC says the first harvest could come around mid-2028.

## What is being built in Pandawai district

The site covers about 2,150 hectares in Palakahembi village and Watumbaka urban village, in Pandawai district, according to KKP. CNBC lists 12 clusters, 1,536 culture ponds, 192 reservoir ponds and 48 cluster wastewater treatment units, plus a seawater intake, a quarantine area, production roads and processing facilities. KKP calls it roughly 20 times larger than its Kebumen farm in Central Java. Antara reported in April that the land was previously savanna.

The investment is US$500 million, about Rp7.2 trillion, financed through foreign private credit. Antara breaks it down as Rp6.1 trillion in foreign loans and Rp1.1 trillion in counterpart rupiah funds. At full operation the farm is meant to produce about 52,800 tonnes of shrimp a year, from two to 2.5 cycles annually.

## Jobs and local hiring

KKP opened online recruitment for 3,000 local workers on 10 February 2026, with free training. In April, Nyoman Radiarta, who heads KKP's human resources agency, said the classes would last 12 to 16 months. On 2 September, Muhammad Qodari, head of the Government Communication Agency, said the project is projected to absorb about 7,000 workers across its industrial chain, which InvestorTrust says includes hatcheries, feed mills, cold storage and ice factories. Arif Maramba, head of Palakahembi village, called the project a "new economic engine" in KKP's press release.

## What it means

The farm is an industrial project, not a tourism one, but it will shape the [East Sumba](https://thesumbatimes.com/en/places/east-sumba-regency/) economy, labour market and coastline around [Waingapu](https://thesumbatimes.com/en/places/waingapu-town/) for years. If it works as planned, it could increase demand for housing, transport and services; that is our reading, not a claim in the reports. The CNBC report does not address environmental impact or effects on neighbouring communities, and KKP's press release mentions only a wastewater treatment plant, greening and good aquaculture practices. We will report on those points when they are published. For other large works on the island, see [what is being built in Sumba](https://thesumbatimes.com/en/projects/what-is-being-built-in-sumba/).

## Sources

- [KKP: KKP Mulai Pembangunan Tambak Udang Terintegrasi di Waingapu (press release, 11 Feb 2026)](https://kkp.go.id/news/news-detail/kkp-mulai-pembangunan-tambak-udang-terintegrasi-di-waingapu-gnx3.html)
- [CNBC Indonesia: Trenggono Bangun Tambak Udang Raksasa di NTT, Begini Progresnya (8 Nov 2026)](https://www.cnbcindonesia.com/news/20261107213133-4-783215/trenggono-bangun-tambak-udang-raksasa-di-ntt-begini-progresnya)
- [InvestorTrust: Proyek Tambak Udang Terintegrasi Waingapu Senilai Rp 7,2 Triliun Beroperasi 2028, Serap 7.000 Tenaga Kerja (3 Sep 2026)](https://investortrust.id/business/115050/proyek-tambak-udang-terintegrasi-waingapu-senilai-rp-7-2-triliun-beroperasi-2028-serap-7000-tenaga-kerja)
- [ANTARA: Tambak udang Waingapu ditargetkan mulai beroperasi tahun depan (1 Apr 2026)](https://www.antaranews.com/berita/5504485/tambak-udang-waingapu-ditargetkan-mulai-beroperasi-tahun-depan)
- [ANTARA: KKP pastikan tenaga kerja lokal terlibat dalam tambak udang Waingapu (2 Apr 2026)](https://www.antaranews.com/berita/5507349/kkp-pastikan-tenaga-kerja-lokal-terlibat-dalam-tambak-udang-waingapu)
- [ANTARA: KKP buka rekrutmen 3.000 tenaga kerja dukung tambak udang di Waingapu (11 Feb 2026)](https://jogja.antaranews.com/berita/804642/kkp-buka-rekrutmen-3000-tenaga-kerja-dukung-tambak-udang-di-waingapu)